Contact Us

Use the form on the right to contact us.

 

         

123 Street Avenue, City Town, 99999

(123) 555-6789

email@address.com

 

You can set your address, phone number, email and site description in the settings tab.
Link to read me page with more information.

September 2017

Sunday, September 24 – Saturday, September 30, 2017: Project Photos

Sunday, September 24 – Saturday, September 30, 2017: Project Updates
(There is no work scheduled for Saturday, September 30th)

Sunday September 24, 2017

  • No construction activities.

Monday September 25, 2017

  • Contractor FMCC worked at the west side of the intersection of 8th Street NE and Monroe Street, placed geotextile fabric, reinforcement and tie bars and poured 10” concrete for utility cut repair.

Tuesday September 26, 2017

  • Contractor worked at the intersection of 9th Street NE and Monroe Street NE, backfilling around the east vault manhole with GAB and placed temporary 12.5mm asphalt to restore the roadway.

Wednesday September 27, 2017

  • Contractor worked at the intersection of 9th Street NE and Monroe Street NE, excavating /trenching for 6-way fiberglass conduits.

Thursday September 28, 2017

  • Contractor worked east of  the intersection of 9th Street NE and Monroe Street NE, excavating and installing  2-way 4” PVC pipes.

Friday September 29, 2017

  • Contractor continued trenching and laying 2-way 4” PVC pipes east of the intersection of 9th Street NE and Monroe Street NE.
  • Contractor removed steel plates at the intersection of Monroe Street and 8th Street and placed 2” of temporary asphalt for utility cuts.

Saturday September 30, 2017

  • No construction activities.

PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th – 8th Street NE for the period of 8/14/17 – 11/11/17.
NO PARKING signs have been posted. 

Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.


Sunday, September 17 – Saturday, September 23, 2017: Project Photos

Sunday, September 17 – Saturday, September 23, 2017: Project Updates
(There is no work scheduled for Saturday, September 23rd)

Sunday September 17, 2017

  • No construction activities.

Monday September 18, 2017

  • Contractor continued trenching for fiberglass conduits west of the intersection of 8th Street NE and Monroe Street NE.
  • At east side: Intersection of 9th Street NE and Monroe Street NE, the contractor continued clean up.

Tuesday September 19, 2017

  • Contractor continued trenching for fiberglass conduits from the west vault manhole towards the split.
  • At east side: Intersection of 9th Street NE and Monroe Street NE, the contractor continued excavation for 12-way fiberglass conduits from the vault manhole to the split.

Wednesday September 20, 2017

  • Contractor continued trenching for fiberglass conduits from the west vault manhole towards the split; and laid and encased fiberglass.
  • At east side: Intersection of 9th Street NE and Monroe Street NE, the contractor continued excavation for 12-way fiberglass conduits from the vault manhole to the split.

Thursday September 21, 2017

  • Contractor encased the 12-way up to the split at the west side.
  • At east side: Contractor poured concrete to encase 5”, 12-way fiberglass conduits.

Friday September 22, 2017

  • Contractor backfilled trench cut for 12-way 5” fiberglass conduits at the intersection of 8th Street NE and Monroe Street NE, placed GAB and Geotextile fabric. Tie bars were drilled and bottom rebar placed. 10” PCC poured for roadway base restoration.

Saturday September 23, 2017

  • No construction activities.

PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th – 8th Street NE for the period of 8/14/17 – 11/11/17.
NO PARKING signs have been posted. 

Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.


Sunday, September 10 – Saturday, September 16, 2017: Project Photos

Sunday, September 10 – Saturday, September 16, 2017: Project Updates
(There is no work scheduled for Saturday, September 16th)

Sunday September 10, 2017

  • No construction activities.

Monday September 11, 2017  

  • Contractor continued trenching for fiberglass conduits at the intersection of Monroe ST NE and 9th Street.

Tuesday September 12, 2017

  • Contractor continued trenching for fiberglass conduits at the intersection of Monroe ST NE and 9th Street.

Wednesday September 13, 2017

  • Contractor continued placement of Pepco fiberglass conduits at the intersection of Monroe ST NE and 9th Street.

Thursday September 14, 2017

  • Contractor started the excavation on the West side to connect the West Pepco Vault manhole with the existing Vault manhole in the Bozzuto property west of 8th Street.

Friday September 15, 2017

  • Contractor continued trenching for fiberglass conduits West of the intersection of 8thStreet, NE and Monroe ST NE.

  • Contractor continued to excavate for the 2-way PVC at the intersection of 9th ST and Monroe ST NE.

Saturday September 16, 2017

  • No construction activities.

PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th – 8th Street NE for the period of 8/14/17 – 11/11/17.
NO PARKING signs have been posted. 

Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.


Sunday, September 3 – Saturday, September 9, 2017: Project Photos

Sunday, September 3 - Saturday, September 9, 2017: Project Updates
(Work is scheduled for Saturday, September 9th) 

Sunday September 3, 2017

  • No construction activities.

Monday September 4, 2017

  • Labor Day – No construction activities.

Tuesday September 5, 2017

  • Contractor continued trenching for fiberglass conduits at the intersection of Monroe Street NE and 9th Street NE. Because of underground utilities, work is being done by hand to go below water/sewer line present. Another unidentified pipe was found on 9th Street by the west curb. DC Water was called to identify the line. DC Water to come on Tuesday 9/5/2017.  

Wednesday September 6, 2017

  • Contractor continued trenching for fiberglass conduits at the intersection of Monroe Street NE and 9th Street NE and also west of the intersection of 8th Street NE and Monroe Street NE. Contractor used two crews (one at each end of the bridge). Contractor has installed 15ft of 6-way 5” fiberglass conduits at the intersection of 9th Street and Monroe – installation was done 9/5/2017
  • The MOT set up worked accordingly and each end had a flagger to direct traffic.
  • It started to rain at 11:30 AM. Contractor covered opened trenches with steel plates and suspended work around 12:30 PM.

Thursday September 7, 2017

  • Contractor continued trenching for fiberglass conduits at the intersection of Monroe Street NE and 9th Street NE and also west of the intersection of 8th Street NE and Monroe Street NE. Contractor used two crews (one at each end of the bridge). In addition to the civil crew, contractor had (1) electrical crew on 9th Street NE to continue excavation.

Friday September 8, 2017

  • Contractor continued trenching for fiberglass conduits at the intersection of Monroe Street NE and 9th Street NE and also west of the intersection of 8th Street NE and Monroe Street NE. Contractor used two crews (one at each end of the bridge). The electrical crew is working on 9th Street NE to continue excavation.

Saturday September 9, 2017

  • Contractor continued trenching for fiberglass conduits at the intersection of Monroe Street NE and 9th Street NE and also west of the intersection of 8th Street NE and Monroe Street NE.

PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th – 8th Street NE for the period of 8/14/17 – 11/11/17. NO PARKING signs have been posted. 

Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.


Sunday, August 27 – Saturday, September 2, 2017: Project Photos

Sunday, August 27 – Saturday, September 2, 2017: Project Updates
(There is no work scheduled for Saturday, September 2nd)

Sunday August 27, 2017

  • No construction activities.

Monday August 28, 2017

  • Contractor worked on riser forming work for the Vault manhole west of the intersection of Monroe Street and 8th Street NE.
  • Contractor continued trenching for fiberglass conduits to connect the east Pepco Vault at the intersection of Monroe Street and 9th Street NE.

Tuesday August 29, 2017

  • No construction activities due to rain.

Wednesday August 30, 2017

  • Contractor continued trenching for fiberglass conduits at the intersection of Monroe Street NE and 9th Street NE. Because of underground utilities, work is being done by hand to go below water/sewer line present.

Thursday August 31, 2017

  • Contractor FMCC continued trenching for fiberglass conduits at the east side of the bridge – Conduit will go from Pepco vault in 901 Monroe property to the newly placed manhole at the intersection of Monroe and 9th Street NE.

Friday September 1, 2017

  • Contractor FMCC continued trenching for fiberglass conduits at the east side of the bridge – to go under existing utilities, contractor is hand digging.

Saturday September 2, 2017

  • No construction activities.

PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th – 8th Street NE for the period of 8/14/17 – 11/11/17. NO PARKING signs have been posted. 

Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.