JUNE 2019

Sunday, June 23 – Saturday, June 29, 2019: Project Photos

Sunday, June 23 – Saturday, June 29, 2019: Project Updates
(There was no construction activity completed on Sunday, June 23rd or Saturday, June 29th)

  • The following activities were completed for this week: continued trench excavation for the Pepco duct bank and prep for wing wall repair at the west approach; continued 12” gas main trench backfilling at both approaches; installed new 6-way 5” fiber conduit and placed concrete encasement; installed rebar for wing wall repair; placed concrete for southwest wing wall repair and continued grading for east approach slab; continued rebar installation for the west approach slab and continued form work installation for the south side bridge parapet wall; placed concrete for the west approach and continued fine grading for the east approach slab; removed 4” temporary gas main from the north side bridge parapet. The bridge was closed from Friday, June 28 at 9:00 pm to Saturday, June 29 at 5:00 AM to work on the 4” gas main removal. All related equipment and material were demobilized from the site.

PLEASE NOTE:

  • Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.

  • Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.  


Sunday, June 16 – Saturday, June 22, 2019: Project Photos

Sunday, June 16 – Saturday, June 22, 2019: Project Updates
(There was no construction activity completed on Sunday, June 16th)

  • The following activities were completed for this week: continued preparation work for the bridge concrete placement; continued 12” gas main trench backfilling at east and west approaches; poured concrete; continued preparation work for the bridge sidewalk concrete placement; placed the bridge sidewalk concrete; and started west approach slab demolition and PCC parapet formwork installation.

PLEASE NOTE:

  • Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.

  • Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.  


Sunday, June 9 – Saturday, June 15, 2019: Project Updates
(There was no construction activity completed on Sunday, June 9th)

  • The following activities were completed for this week: continued 12” gas main installation at both ends of the bridge including testing, tie-ins and placed the new gas main in service on the bridge; continued 12” gas main trench backfilling at the east and west approaches; continued preparation work for the bridge concrete placement; placed the bridge deck concrete on spans 1 and 3; placed the bridge sidewalk concrete over span 2; stripped form work for the previously placed deck sections and prepped for deck placement and sidewalk placement. The bridge was closed to traffic from Thursday, June 13 at 11:00 pm to Friday, June 14 at 9:00 AM for the deck concrete setting time. 

PLEASE NOTE:

  • Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.

  • Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.  


Sunday, June 2 – Saturday, June 8, 2019: Project Photos

 Sunday, June 2 – Saturday, June 8, 2019: Project Updates
(There was no construction activity completed on Sunday, June 2nd)

  • The following activities were completed for this week: continued bridge deck rebar installation (phase 2); continued 12” gas main installation (east and west end approaches/phase 2); performed form work and bulkhead installation; completed preparation for the bridge deck concrete placement (phase 2); installation of the Bidwell machine and railing and bulkhead form for the pour sequences; performed concrete repairs on the existing abutment; and placed the concrete on span 2 and completed deck concrete placement sequence #1 (phase 2). The bridge was closed to traffic from Friday, June 7 at 11:00 pm to Saturday, June 8 at 11:00 am to complete this activity.      

PLEASE NOTE:

  • Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.

  • Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.