Sunday, October 29 – Saturday, November 4, 2017: Project Photos

Sunday, October 29 – Saturday, November 4, 2017: Project Updates
(There is no work scheduled for Saturday, November 4th)

  • Continued coordination efforts with various agencies/stakeholders and Maintenance of Traffic.

PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th – 8th Street NE for the period of 8/14/17 – 11/11/17.
NO PARKING signs have been posted. 

Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.


Sunday, October 22 – Saturday, October 28, 2017: Project Photos

Sunday, October 22 – Saturday, October 28, 2017: Project Updates
(There is no work scheduled for Saturday, October 28th)

  • FMCC surveyors on site to continue baseline, bridge control line and street lighting manhole and conduit survey.

PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th – 8th Street NE for the period of 8/14/17 – 11/11/17.
NO PARKING signs have been posted. 

Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.


Sunday, October 15 – Saturday, October 21, 2017: Project Photos

Sunday, October 15 – Saturday, October 21, 2017: Project Updates
(There is no work scheduled for Saturday, October 21st)

Sunday October 15, 2017

  • No construction activities.

Monday October 16, 2017

  • Contractor worked at the west side of the intersection of 8th Street NE and Monroe Street NE, and east side of 9th Street and Monroe Street NE, backfilling, compacting installed 4-way PVC conduits, placed geo-fabric, reinforcement and poured 10’’ of concrete for utility cuts repair.

Tuesday October 17, 2017

  • Contractor worked at the south side of the intersection of 9th Street and Monroe Street NE, placement of 4’’ asphalt pavement for utility cuts repair, saw cut asphalt at the east of the intersection for conduits installation trenching.

Wednesday October 18, 2017

  • Contractor worked at the east side of the intersection of 9th Street NE and Monroe Street NE, excavating and installing manhole #25.

Thursday October 19, 2017

  • Contractor worked along Monroe Street NE from 8th Street to 10th Street, survey marking layout for manholes, utility cuts, and barriers locations.

Friday October 20, 2017

  • Contractor continued working along Monroe Street NE from 8th Street to 9th Street, survey marking layout for manholes, utility cuts, and bridge control lines.

Saturday October 21, 2017

  • No construction activities.

PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th – 8th Street NE for the period of 8/14/17 – 11/11/17.
NO PARKING signs have been posted. 

Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.


Sunday, October 8 – Saturday, October 14, 2017: Project Photos

Sunday, October 8 – Saturday, October 14, 2017: Project Updates
(There is no work scheduled for Saturday, October 14th)

Sunday October 8, 2017

  • No construction activities.

Monday October 9, 2017

  • No construction activities due to the rain.

Tuesday October 10, 2017

  • Contractor worked at the west side of the intersection of 8th Street NE and Monroe Street NE, backfilled, compacted installed fiber glass and PVC conduits, placed geo-fabric, reinforcement and poured 10’’ of concrete for utility cuts repair.

Wednesday October 11, 2017

  • Contractor worked at the west side of the intersection of 8th Street NE and Monroe Street NE, continued backfilling, compacting installed fiber glass conduits, placed geo-fabric, reinforcement and poured 10’’ of concrete for utility cuts repair.

Thursday October 12, 2017

  • Contractor worked at the east side of the intersection of 9th Street and Monroe Street NE, installed, encased with concrete 2-way PVC conduits; 4” of asphalt pavement for utility cuts repair.

Friday October 13, 2017

  • Contractor worked at the west side of the intersection of 8th Street and Monroe Street NE, continued installation of 2-way PVC conduits, 4’’ asphalt pavement for utility cuts repair.

Saturday October 14, 2017

  • Update: No construction activities.     

PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th – 8th Street NE for the period of 8/14/17 – 11/11/17.
NO PARKING signs have been posted. 

Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.


Sunday, October 1 – Saturday, October 7, 2017: Project Photos

Sunday, October 1 – Saturday, October 7, 2017: Project Updates
(There is no work scheduled for Saturday, October 7th)

Sunday October 1, 2017

  • No construction activities.

Monday October 2, 2017

  • Contractor FMCC worked at the west side of the intersection of 9th Street NE and Monroe Street backfilled, compacted installed fiberglass conduits with GAB, and placed temporary asphalt for utility cut repair.

Tuesday October 3, 2017

  • Contractor worked at the east side of the intersection of 9th Street NE and Monroe Street NE, backfilled, compacted installed PVC conduits, placed geo-fabric, reinforcement and poured 10’’ of concrete for utility cut repair.

Wednesday October 4, 2017

  • Contractor worked at the east side of the intersection of 9th Street NE and Monroe Street NE, excavating/trenching, installing, and encasement of 1-way and 2-way PVC.

Thursday October 5, 2017

  • Contractor worked at south side and east side of the intersection of 9th Street NE and Monroe Street NE, excavating, backfilling, compaction, placed geo-fabric, reinforcement and poured 10’’ of concrete for roadway restoration and for utility cut repair.
  • West side of the intersection of 8th Street and Monroe Street NE - installing 8-way fiberglass conduits.

Friday October 6, 2017

  • Contractor continued installation of 8-way fiberglass conduits at the west side of the intersection of 8th Street and Monroe Street NE.

Saturday October 7, 2017

  • No construction activities.

PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th – 8th Street NE for the period of 8/14/17 – 11/11/17.
NO PARKING signs have been posted. 

Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.