Sunday, November 25 – Saturday, December 1, 2018: Project Photos
Sunday, November 25 – Saturday, December 1, 2018: Project Updates
(There was no construction activity completed on Sunday, November 25th or Saturday, December 1st.)
The contractor is currently working on the south side of Monroe Street NE Bridge within the construction zone. The following was completed during the above period: continued prep work for demolition of the existing Monroe Street Bridge (Phase 2); started installing the protection shield for the gas main in Span 2; continued removing the grout from the joints between the box beam girders; and saw cut the existing sidewalk and parapet wall in Span 2. There were no lane closures needed to complete this week’s construction activity. Traffic was maintained with two open-lanes, eastbound and westbound.·
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, November 18 – Saturday, November 24, 2018: Project Photos
Sunday, November 18 – Saturday, November 24, 2018: Project Updates
(There was no construction activity completed on Sunday, November 18th; Thursday, November 22nd - Friday, November 23rd - Thanksgiving Day Holiday Observed; or Saturday, November 24th.)
The contractor is currently working on the south side of Monroe Street NE Bridge within the construction zone. The following was completed during the above period: saw cut and demolished existing parapet wall over the CSX tracks (Spans 1 & 3); demolished existing back walls at east abutment (Phase 2); and drilled holes into existing beams for lifting over CSX tracks (Spans 1 & 3). There were no lane closures needed to complete this week’s construction activity. Traffic was maintained with two open-lanes, eastbound and westbound.
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, November 11 – Saturday, November 17, 2018: Project Photos
Sunday, November 11 – Saturday, November 17, 2018: Project Updates
(There was no construction activity completed on Sunday, November 11th or Monday, November 12th - Veterans Day Holiday Observed. There was construction activity completed on Saturday, November 17th.)
The contractor is currently working on the south side of Monroe Street NE Bridge within the construction zone. The following was completed during the above period: demolished existing back walls at abutments; drilled holes into existing beams for lifting over CSX tracks (Spans 1 & 3); worked to connect power to new traffic and pedestrian signal at 8th Street intersection; installed the protection shield beneath the existing gas main over CSX tracks; saw cut and removed existing parapet over the CSX tracks (south side, Spans 1 & 3); and saw cut and removed existing sidewalk over the CSX tracks (south side, Spans 1 & 3). There were no lane closures needed to complete this week’s construction activity. Traffic was maintained with two open-lanes, eastbound and westbound.
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, November 4 – Saturday, November 10, 2018: Project Photos
Sunday, November 4 – Saturday, November 10, 2018: Project Updates
(There was no construction activity completed on Sunday, November 4th or Saturday, November 10th)
The contractor is currently working on the south side of Monroe Street NE Bridge within the construction zone. The following was completed during the above period: began to saw cut and remove existing fence from the south side of Monroe Street Bridge; installed temporary wooden fence on the south side and painted with retro reflective red and white paint; set up for the bridge fence removal and installed the temporary protection shield in bay 13 for the existing gas main; secured the work zone with traffic drums; began removal of the existing bridge fence and mobilized the snooper and snooper truck for proposed demolition; installed the temporary scaffolding along the south side of the west abutment wall A-1; began core drilling for the proposed lifting lugs; began saw cutting existing parapet for the demolition (south side, Span 1 & 3); and worked on concrete repair prep work (abutment A1, Phase 2). There were no lane closures needed to complete this week’s construction activity. Traffic was maintained with two open-lanes, eastbound and westbound.
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.