APRIL 2019
Sunday, April 28 – Saturday, May 4, 2019: Project Photos
Sunday, April 28 – Saturday, May 4, 2019: Project Updates
(There was no construction activity completed on Sunday, April 28th or Saturday, May 4th)
The contractor completed the following activities for this week: continued pier 2 cap form removal (phase 2); continued overhang brackets and wood form removal from the north side (phase 1); continued type 4 concrete repair at the west abutment (A); continued welding and coating the 12” gas main in the staging area between 7th & 8th Street; and started steel beam installation. There were activities performed this week that required the overnight closure (11:00pm - 5:00am) of all lanes of traffic on the bridge.
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, April 21 – Saturday, April 27, 2019: Project Photos
Sunday, April 21 – Saturday, April 27, 2019: Project Updates
(There was no construction activity completed on Sunday, April 21st)
The contractor completed the following activities for this week: continued pier cap form removals (Phase 2); continued west abutment (A) backwall form removal (Phase 2); continued the removel of the overhang brackets and wood form on the north side (Phase 1); and continued type 4 concrete repair at the west abutment (A-Phase 2). In addition, the WGL contractor was on site welding the 12” gas main in the staging area between 7th & 8th Streets. There were no lane closures needed to complete activities for this weekly period and traffic was maintained with two open-lanes, eastbound and westbound.
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, April 14 – Saturday, April 20, 2019: Project Photos
Sunday, April 14 – Saturday, April 20, 2019: Project Updates
(There was no construction activity completed on Sunday April 14th, Friday April 19th due to rain or Saturday April 20th)
The contractor completed the following activities for this week: continued pier cap form and rebar installation (Phase 2); continued abutment A back wall form and rebar installation (Phase 2); continued the removel of the overhang brackets and wood form on the north side (Phase 1); continued type 2 concrete repair at the pier 1 crash wall; and type 4 concrete repair at the west abutment A (Phase 2). There were no lane closures needed to complete activities for this weekly period and traffic was maintained with two open-lanes, eastbound and westbound. ·
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, April 7 – Saturday, April 13, 2019: Project Photos
Sunday, April 7 – Saturday, April 13, 2019: Project Updates
(There was no construction activity completed on Sunday, April 7th or Saturday, April 13th)
The contractor completed the following activities for this week as a part of phase 2 demolition: continued pier 2 cap form and rebar installation; continued abutment B back wall form removal and phase 1 overhang brackets and wood form removal from the north side; and resumed type 4 concrete repair at the west abutment (phase 2). There were no lane closures needed to complete activities for this weekly period and traffic was maintained with two open-lanes, eastbound and westbound.
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, March 31 – Saturday, April 6, 2019: Project Photos
Sunday, March 31 – Saturday, April 6, 2019: Project Updates
(There was no construction activity completed on Sunday, March 31st or Saturday, April 6th)
The contractor completed the following activities for this week as a part of phase 2 demolition: continued removal of the steel forms from the columns at pier 1; continued steel forms and rebar installation for the pier 2 cap. On Friday, March 29, the bridge was closed from 2:00 am until 5:30 am to complet the pier cap concrete placement. There were no other lane closures needed to complete activities for the remainder of this weekly period and traffic was maintained with two open-lanes, eastbound and westbound.
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.