MAY 2019

Sunday, May 26 – Saturday, June 1, 2019: Project Photos

Sunday, May 26 – Saturday, June 1, 2019: Project Updates
(There was no construction activity completed on Sunday, May 26th or Monday, May 27th due to the Memorial Day Holiday)

  • The contractor completed the following activities for this week: installation of the wood deck form work for Phase 2; demolition of the east existing approach slab and trench excavation for the proposed 6-way Pepco conduit duct bank; placement of 6-way Pepco conduit and poured concrete for the duct bank at the east abutment; installation of expansion dam at the east approach; installation of shear studs on beams at spans 1 and 3; installation of 12” gas main at west end approach; caulking and sealing deck form to prevent concrete grout leakage on to the WMATA and CSX tracks; and installation of rebar for bridge deck.

PLEASE NOTE:

  • Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.

  • Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.  


Sunday, May 19 – Saturday, May 25, 2019: Project Photos

Sunday, May 19 – Saturday, May 25, 2019: Project Updates
(There was no construction activity completed on Sunday, May 19th or Saturday, May 25th)

  • The contractor completed the following activities for this week: continued utility supports installation and wood and SIP deck form installation for steel beams at spans 1 and 3; continued preparation work for the 12” gas main tie in at the west abutment; and installed debris net under span 2 over the WMATA platform. 

PLEASE NOTE:

  • Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.

  • Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.  


Sunday, May 12 – Saturday, May 18, 2019: Project Photos

Sunday, May 12 – Saturday, May 18, 2019: Project Updates
(There was no construction activity completed on Sunday, May 12th or Saturday, May 18th)

  • The contractor completed the following activities for this week: continued utility supports installation and torquing bolted connection from steel beams at spans 1 and 3; continued preparation work for the 12” gas main tie in at the west abutment; started overhang form installation for the steel beam at spans 1 and 3; and started shim plates installation at pier 1 under the steel beam.·      

PLEASE NOTE:

  • Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.

  • Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.  


Sunday, May 5 – Saturday, May 11, 2019: Project Photos

Sunday, May 5 – Saturday, May 11, 2019: Project Updates
(There was no construction activity completed on Sunday, May 5th or Saturday, May 11th)

  • The contractor completed the following activities for this week: continued diaphragms installation and torqueing the bolted connection from the steel beams at spans 1 to 3; continued removing form which was installed for type 4 repairs and cleaned up at west abutment (A); continued preparation work for the 12” gas main installation; and completed the installation of the 12” gas main. There were activities performed this week that required the overnight closure (11:00pm - 7:00am) of all lanes of traffic on the bridge.

PLEASE NOTE:

  • Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.

  • Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.