MAY 2019
Sunday, May 26 – Saturday, June 1, 2019: Project Photos
Sunday, May 26 – Saturday, June 1, 2019: Project Updates
(There was no construction activity completed on Sunday, May 26th or Monday, May 27th due to the Memorial Day Holiday)
The contractor completed the following activities for this week: installation of the wood deck form work for Phase 2; demolition of the east existing approach slab and trench excavation for the proposed 6-way Pepco conduit duct bank; placement of 6-way Pepco conduit and poured concrete for the duct bank at the east abutment; installation of expansion dam at the east approach; installation of shear studs on beams at spans 1 and 3; installation of 12” gas main at west end approach; caulking and sealing deck form to prevent concrete grout leakage on to the WMATA and CSX tracks; and installation of rebar for bridge deck.
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, May 19 – Saturday, May 25, 2019: Project Photos
Sunday, May 19 – Saturday, May 25, 2019: Project Updates
(There was no construction activity completed on Sunday, May 19th or Saturday, May 25th)
The contractor completed the following activities for this week: continued utility supports installation and wood and SIP deck form installation for steel beams at spans 1 and 3; continued preparation work for the 12” gas main tie in at the west abutment; and installed debris net under span 2 over the WMATA platform.
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, May 12 – Saturday, May 18, 2019: Project Photos
Sunday, May 12 – Saturday, May 18, 2019: Project Updates
(There was no construction activity completed on Sunday, May 12th or Saturday, May 18th)
The contractor completed the following activities for this week: continued utility supports installation and torquing bolted connection from steel beams at spans 1 and 3; continued preparation work for the 12” gas main tie in at the west abutment; started overhang form installation for the steel beam at spans 1 and 3; and started shim plates installation at pier 1 under the steel beam.·
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, May 5 – Saturday, May 11, 2019: Project Photos
Sunday, May 5 – Saturday, May 11, 2019: Project Updates
(There was no construction activity completed on Sunday, May 5th or Saturday, May 11th)
The contractor completed the following activities for this week: continued diaphragms installation and torqueing the bolted connection from the steel beams at spans 1 to 3; continued removing form which was installed for type 4 repairs and cleaned up at west abutment (A); continued preparation work for the 12” gas main installation; and completed the installation of the 12” gas main. There were activities performed this week that required the overnight closure (11:00pm - 7:00am) of all lanes of traffic on the bridge.
PLEASE NOTE:
Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.