July 2018
Sunday, July 22 – Saturday, July 28, 2018: Project Photos
Sunday, July 22 – Saturday, July 28, 2018: Project Updates
(There is work scheduled for Saturday, July 28th)
Sunday July 22 2018 - Friday July 27, 2018:
The contractor worked at the north side of Monroe Street Bridge NE within the construction zone, pouring pier caps concrete and continued existing concrete repair on abutments. DDOT and PEPCO continued preparation work for the electrical and communication cable relocation on the bridge. All traffic maintained with two open lanes eastbound and westbound with the exception of Wednesday, July 25th when the Bridge was temporarily closed from 10:00 AM to 4:00 PM to set up the crane for the pier cap placement.
Saturday, July 28, 2018:
- The Monroe Street Bridge was closed on Saturday until 9:00 PM to set the crane and install the beams.
PLEASE NOTE:
- Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
- Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, July 15 – Saturday, July 21, 2018: Project Photos
Sunday, July 15 – Saturday, July 21, 2018: Project Updates
(There is work scheduled for Saturday, July 21st)
Sunday July 15 2018 - Saturday July 21, 2018:
The contractor worked at the north side of Monroe Street NE Bridge within the construction zone, installing and securing proposed reinforcing steel cage for piers cap. All traffic maintained with two open-lanes eastbound and westbound.
PLEASE NOTE:
- Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
- Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, July 8 – Saturday, July 14, 2018: Project Updates
(There is no work scheduled for Saturday, July 14th)
Sunday July 8, 2018 - Friday July 14, 2018:
The contractor worked at the North Side of Monroe St Bridge NE within the construction zone, installing and securing proposed reinforcing steel cage for piers cap. Contractor also excavated and installed proposed utility underground conduits, encased, backfilled and compacted at the intersection of 8th Street and Monroe Street NE. All traffic maintained with two open-lanes eastbound and westbound.
PLEASE NOTE:
- Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
- Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.
Sunday, July 1 – Saturday, July 7, 2018: Project Updates
(There is no work scheduled for Saturday, July 7th)
Sunday July 1, 2018 - Friday July 6, 2018:
The contractor worked at the north side of Monroe Street NE Bridge within the construction removing piers and back wall at Abutments. Contractor also excavated and installed proposed conduits, encased, backfilled and compacted at the intersection of 8th Street and Monroe Street NE. Trenches secured using steel plates. All traffic maintained with two open-lanes eastbound and westbound.
PLEASE NOTE:
- Due to construction, there is no parking on Monroe Street from 7th - 8th Street NE.
- Signs directing motorist and bicyclist have been posted. Please stay alert and obey signage when traveling through this area.